Clearing the Path: Reforming Procurement to Accelerate Defense Innovation

Defense Posture and Global ThreatsHouse Oversight and Government Reform Subcommittee on Military and Foreign Affairs · 2025-06-11 · 119th Congress
The Subcommittee on Military and Foreign Affairs held this hearing to examine why the Department of Defense's acquisition process is slow, costly, and often blocks innovative technologies from reaching the field — including the so-called "valley of death" between prototype and production. Begins at 0:16:50
Transcript
Highlights

Title

Reforming DoD acquisition to speed defense innovation and cut waste

Purpose

The Subcommittee on Military and Foreign Affairs held this hearing to examine why the Department of Defense's acquisition process is slow, costly, and often blocks innovative technologies from reaching the field — including the so-called "valley of death" between prototype and production. Four witnesses testified on regulatory burden, iterative development, workforce shortcomings, and IT modernization as paths to reform, drawing on a GAO report on weapons programs released the same day. Begins at0:16:50

Who spoke

Chairman William Timmons (R-SC)0:16:50: Opened by describing the acquisition process as opaque and punishing to startups, citing seven consecutive failed DoD audits0:19:03; later questioned witnesses on the "valley of death"0:46:46 and on continuing resolutions' impact on procurement1:34:38.

Ranking Member Sudarshan Subramanyam (D-VA)0:19:32: Highlighted Virginia's chip and circuit-board manufacturers, cited a GAO finding that it can take over a decade to deliver capabilities0:21:50, and criticized cuts to DOT&E staff and contractor support0:23:26; closed by pressing for actual reform rather than repeated talk1:49:47.

Ms. Margaret Boatner (Aerospace Industries Association)0:26:21: Said major acquisition programs now take an average of 11 years0:27:35, that the FAR plus DFARS totals more than 5,000 pages0:27:35, and that roughly 40% of small businesses left the DoD market from 2011–20200:28:25; later said continuing resolutions force reduced procurement quantities and raise per-unit costs0:34:38.

Mr. Eric Snelgrove (National Defense Industrial Association)0:30:55: Said venture funding rounds average just 12 months, far shorter than DoD's procurement cycle, driving startups to abandon defense work0:31:56; recommended a commercial-first acquisition approach, investment in manufacturing resilience, and protecting basic research funding0:32:56.

Ms. Shelby Oakley (GAO)0:35:57: Presented GAO's 23rd annual weapons assessment, finding DoD plans to spend at least $2.4 trillion on its portfolio while capability now takes nearly 12 years to deliver, a year and a half longer than last year0:36:57; said DoD's adaptive acquisition framework has not made programs finish faster0:37:55 and urged a wholesale shift to iterative development0:40:18.

Mr. Moshe Schwartz (Coalition for Government Procurement)0:40:42: Argued the core problems are the acquisition workforce and outdated IT systems, not just regulation0:43:26; described an Army IT system that could not communicate with the Defense Logistics Agency's system, leaving 90% of needed spare parts undelivered0:45:30.

Rep. Andy Biggs (R-AZ)0:56:52: Criticized reinstated project labor agreements as sidelining non-union contractors in a state where 97% of workers are non-unionized0:58:17; said Congress lacks incentive to force change and called the body "probably irredeemable"0:59:39.

Rep. Stephen Lynch (D-MA)1:01:25: Asked about roughly 121,000 DoD layoffs since January and a deferred resignation program that removed 21,000 employees, 83% with a bachelor's degree or higher1:02:19; pressed on IT investment, citing the Defense Travel System's roughly $1 billion in improper payments1:06:40.

Rep. James Comer (R-KY)1:07:54: Asked how procurement modernization affects the "Golden Dome" missile defense system and the role of public-private partnerships1:07:54.

Rep. Glenn Ivey (D-MD)1:11:58: Cited $10.8 billion in documented DoD fraud, criticized the firing of the DoD Inspector General, and called on Secretary Hegseth to testify, noting the Marine Corps is the only branch to pass an audit1:12:18.

Rep. Eli Crane (R-AZ)1:17:30: Questioned Boatner about the revolving door between military officers and contractors, citing the Littoral Combat Ship and a defense HR software program 780% over budget1:18:30; later pressed Oakley on why GAO projects DoD cannot pass an audit until 20281:45:30.

Rep. Robert Garcia (D-CA)1:22:47: Noted the F-35's projected $2 trillion lifecycle cost and that major defense contractors have shrunk from about 51 to about 101:25:44; asked about risks to the Space Development Agency's Tranche 2/3 programs1:26:40.

Rep. John McGuire (R-VA)1:28:13: Asked about slow DoD qualification of additively manufactured parts and cited a Navy amphibious ship hinge repaired via 3D printing in his district in time for a January 7 deployment1:30:28.

Key moments

Boatner said major defense acquisition programs now average 11 years to deliver capability, driven by a FAR/DFARS regulatory regime exceeding 5,000 pages0:27:350:28:00.

Oakley's GAO report released the same day found DoD plans to spend at least $2.4 trillion on weapons while capability delivery now averages nearly 12 years — 1.5 years longer than last year's assessment0:36:57.

Schwartz described an Army logistics IT system unable to communicate with the Defense Logistics Agency's system, leaving 90% of needed spare parts undelivered, calling it a fundamental IT problem rather than a regulatory one0:45:55.

Snelgrove said startups' 12-month funding cycles outpace DoD's much longer procurement timeline, driving many to pivot away from national security work entirely0:31:560:32:27.

Schwartz estimated procurement reform could save "at least 10%" of costs, while Oakley said hundreds of billions of dollars could be saved based on GAO's annual weapons cost/schedule overrun findings0:55:260:55:56.

Ivey cited $10.8 billion in documented DoD fraud and called for Secretary Hegseth to testify, contrasting the Marine Corps' unique success passing an audit with the rest of the department1:14:311:16:37.

Crane cited the Littoral Combat Ship program and a defense HR software system that ran 780% over budget before termination, tying both to former officers' post-government influence1:18:30; Boatner and Oakley said they were unfamiliar with the specific cases1:20:321:20:58.

Biggs argued Congress has no real incentive to force DoD reform and called the body "probably irredeemable" absent funding tied directly to change0:59:391:01:25.

Crane pressed Oakley on GAO's finding that DoD cannot pass a clean audit until 2028; she attributed delays partly to IT systems never designed with auditability in mind1:46:011:49:18.

Boatner said continuing resolutions cap funding at prior-year levels, forcing reduced procurement quantities, raising per-unit costs, and delaying new contract awards, disproportionately harming small businesses' cash flow1:34:381:35:00.

Metadata

CommitteeHouse Oversight and Government Reform Subcommittee on Military and Foreign Affairs
Chamber / CongressHouse · 119th Congress
Date2025-06-11
TypeHearing
Witnesses
Ms. Margaret Boatner — Vice President / National Security Policy, Aerospace Industries Association
Mr. Eric Snelgrove — Senior Fellow, National Defense Industrial Association
Ms. Shelby Oakley — Director / Contracting and National Security Acquisitions, U.S. Government Accountability Office
Mr. Moshe Schwartz — Defense Fellow, Coalition for Government Procurement
Videoyoutube
Transcript228 caption blocks · 17,580 words · 1:56:37 runtime
EventCongress.gov 118371