Oversight of FERC: Advancing Affordable and Reliable Energy for All Americans

Environmental Permitting and Water InfrastructureHouse Energy and Commerce Subcommittee on Energy · February 3, 2026 · 119th Congress
This House Energy and Commerce Subcommittee on Energy hearing brought all five FERC Commissioners before Congress to testify on the agency's efforts to ensure reliable and affordable electricity amid surging demand from data centers and AI, following closely on the heels of Winter Storm Fern, which knocked out power to over a million homes across the Southeast and Northeast [0:17:33, 0:21:51]. Begins at ▶ 0:16:12
Transcript
Highlights

Title

FERC oversight: grid reliability, affordability, and permitting reform

Purpose

This House Energy and Commerce Subcommittee on Energy hearing brought all five FERC Commissioners before Congress to testify on the agency's efforts to ensure reliable and affordable electricity amid surging demand from data centers and AI, following closely on the heels of Winter Storm Fern, which knocked out power to over a million homes across the Southeast and Northeast▶ 0:17:33▶ 0:21:51. Members from both parties pressed the commissioners on permitting reform, interconnection delays, transmission cost allocation, natural gas pipeline capacity, and how to keep large-load growth from raising residential utility bills. Begins at▶ 0:16:12

Who spoke

• Rep. Bob Latta (R-OH), Subcommittee Chair▶ 0:16:12: Opened by describing a grid "under extreme stress," citing an 11% rise in utility bills in 2025 after a 29% rise over the prior four years▶ 0:17:33, and later pressed commissioners on how to achieve "regulatory certainty"▶ 1:02:40.

• Rep. Kathy Castor (D-FL), Ranking Member▶ 0:20:55: Cited NERC's warning that peak demand could rise over 20% in ten years▶ 0:21:51 and blamed Trump administration actions—Secretary Burgum's sign-off requirement on wind/solar projects and Secretary Wright's cancellation of 300+ energy projects, including a $1.8B Arizona Public Service transmission loan—for making the grid less reliable▶ 0:23:33▶ 0:24:03.

• Rep. Brett Guthrie (R-KY), Full Committee Chairman▶ 0:26:23: Welcomed the commissioners and noted it had been since June 2024 since the Commission last testified before the committee▶ 0:26:52.

• Rep. August Pfluger (R-TX)▶ 0:29:34: Praised a departing committee staffer, Clara Cargill, and highlighted natural gas as the backbone of the Texas grid during the cold snap▶ 0:30:00.

• Rep. Frank Pallone (D-NJ), Ranking Member, Full Committee▶ 0:31:24: Said New Jerseyans are paying 15% more for power and 12% more for gas year-over-year▶ 0:31:53, noted utilities requested a record $31 billion in rate increases last year▶ 0:32:20, and called on FERC to "stand up" to White House pressure on clean energy▶ 0:33:08.

• Chairman Laura Swett, FERC▶ 0:36:55: Emphasized legal durability, said FERC's December PJM order on large-load co-location protects over 67 million Americans▶ 0:41:30, and later said a PJM price cap saved consumers over $12 billion▶ 0:47:05; noted FERC's jurisdiction covers about one-third of a typical utility bill▶ 2:20:16.

• Commissioner David Rosner, FERC▶ 0:41:59: Said FERC fast-tracked over 50GW of shovel-ready power plants under Order 2023▶ 0:44:01 and issued 97 permits, over 30% faster than the last decade▶ 0:45:17; later described MISO's AI-based interconnection software cutting study time from 686 days to under 10 days▶ 1:12:10.

• Commissioner Lindsay See, FERC▶ 0:47:31: Highlighted expanding the blanket-authorization program to hydropower and LNG facilities▶ 0:52:29 and said supply isn't the constraint on LNG exports—infrastructure is▶ 1:15:13.

• Commissioner Judy Chang, FERC▶ 0:52:52: Stressed that large loads must "cover their costs" and not shift costs to other ratepayers▶ 0:55:05, and said transmission bottlenecks, not generation interconnection speed alone, are limiting new supply▶ 0:56:16.

• Commissioner David LaCerte, FERC▶ 0:58:48: In his first hearing, said the Commission approved over 200 orders and 12 major infrastructure projects in its first 90 days, adding 3.3 million dekatherms/day of gas capacity▶ 1:00:57▶ 1:01:25.

• Rep. Randy Weber (R-TX), Vice Chair▶ 1:58:58: Asked about the LNG blanket-certification rulemaking timeline and duplicative FERC/PHMSA safety review▶ 1:59:28▶ 2:01:38.

• Rep. Scott Peters (D-CA)▶ 2:04:45: Pushed on inter-regional transmission cost allocation and suggested FERC, not DOE, should hold siting authority for national interest corridors▶ 2:07:52▶ 2:08:42.

• Rep. Rich McCormick (R-GA)▶ 2:09:36: Highlighted Georgia Power's rate freeze and $102 average customer savings starting 2029▶ 2:10:51.

• Rep. Frank Pallone's colleague, Rep. from NJ 8th District▶ 2:15:17: Discussed the PJM co-location rule and introduced the PRICE Act requiring data centers to bring their own renewable generation▶ 2:18:27.

• Rep. Barry Moore (R-AL)▶ 2:20:40: Asked about rising transmission/distribution costs from state renewable mandates and pipeline capacity constraints, citing that 95% of public gas systems are captive to a single pipeline▶ 2:22:00.

• Rep. Jen Kiggans (R-VA)▶ 2:25:45: Raised environmental-justice concerns about FERC's Office of Public Participation and community engagement timing for disadvantaged communities like Charles City County▶ 2:29:15.

• Rep. Troy Balderson (R-OH)▶ 2:30:37: Asked about LNG exports and winter gas price disparities, noting Northeast prices were 2.4x Appalachian prices after the storm▶ 2:32:39.

• Rep. Brittany Pettersen (D-CO)▶ 2:35:27: Pressed each commissioner on "all of the above" energy support and questioned Chair Swett on whether she supports building transmission▶ 2:38:16.

• Rep. Diana Harshbarger (R-TN)▶ 2:41:10: Raised a FERC Section 4 rate case involving a 123% requested increase versus a 36% justified increase for an East Tennessee pipeline▶ 2:41:40.

• Rep. Laura Friedman (D-CA)▶ 2:46:33: Asked about capital cost recovery and canceled federal grid-resiliency grants shifting costs to ratepayers▶ 2:47:02▶ 2:47:53.

• Rep. Mariannette Miller-Meeks (R-IA)▶ 2:51:48: Asked about PJM's 4.4GW downward revision to its 2028 summer peak forecast and who bears the cost of forecast mismatches▶ 2:54:23.

• Rep. Jake Ellzey (R-TX)▶ 2:57:13: Asked whether ERCOT's faster "connect and manage" interconnection model is preferable to FERC's process▶ 2:58:04.

• Rep. Cliff Bentz (R-OR)▶ 3:02:49: Questioned Commissioner LaCerte on the 23-year Snake River dam relicensing delay and Chinese-made transformer risk▶ 3:03:18▶ 3:04:02.

• Rep. Jake Auchincloss (D-MA)▶ 3:18:34: Detailed Winter Storm Fern's impact on the New England grid, criticized Trump administration offshore wind permit cancellations, and pressed on "legally durable signals" for both generation types▶ 3:20:29▶ 3:21:23.

• Rep. William Timmons (R-SC)▶ 3:23:36: Asked about the Seven County Supreme Court decision's effect on FERC's NEPA practice▶ 3:24:25.

• Rep. Kim Schrier (D-WA)▶ 3:29:02: Raised Western day-ahead market "seams" issues between CAISO's EDAM and SPP Markets+▶ 3:29:57.

• Rep. Laurel Lee (R-FL)▶ 3:34:14: Asked about FERC's Office of Energy Infrastructure Security and cybersecurity coordination▶ 3:34:42.

• Rep. Paul Tonko (D-NY)▶ 3:38:34: Asked about Order 1920 and improved large-load forecasting methods, referencing NERC's 2025 reliability assessment▶ 3:39:27.

• Rep. Nick Langworthy (R-NY)▶ 3:44:24: Criticized New York's all-electric building mandate and DEC's repeated denial of the Constitution Pipeline permits▶ 3:47:34.

• Rep. Max Miller (R-OH)▶ 3:56:39: Raised the Constitution Pipeline dispute again in relation to a Belmont, Ohio cracker plant and asked about EPA coordination▶ 3:58:44.

• Rep. Julie Fedorchak (R-ND)▶ 4:00:01: Presented data showing North Dakota has the lowest energy costs in the country and asked what legislative tools would speed FERC's work▶ 4:03:12.

• Rep. Greg Landsman (D-OH)▶ 4:05:44: Pressed on whether FERC can lower utility profit margins to cut bills and on requiring data centers to pay full infrastructure costs▶ 4:06:38▶ 4:09:01.

• Rep. Morgan Luttrell / Rep. Wesley Hunt (R-TX)▶ 4:11:03: Asked Chair Swett about the April 30, 2026 deadline for the data-center co-location rulemaking▶ 4:12:59.

• Rep. Nathaniel Moran (R-TX)▶ 4:16:46: Cited a $1,000/year cost increase for average families and questioned Commissioner Chang on cost-allocation frameworks for data centers▶ 4:17:14.

• Rep. John Joyce (R-PA)▶ 4:21:56: Asked about load-forecast accuracy for AI/data-center demand and protections for existing generators▶ 4:23:37▶ 4:25:56.

Key moments

• Chairman Swett testified that in December FERC directed PJM to establish transparent co-location rules for AI data centers, affecting over 67 million Americans across the mid-Atlantic▶ 0:41:30.

• Commissioner Rosner said the interconnection process at MISO dropped from 686 days to under 10 days using new AI-based power-flow software, with results accurate to within 0.01%▶ 1:12:10.

• Commissioner Rosner disclosed a new PJM gas plant faced a $1+ billion interconnection upgrade cost requiring over 100 miles of new 345,000-volt transmission line, illustrating transmission scarcity▶ 1:21:05.

• Ranking Member Pallone got all five commissioners to commit "yes" to prioritizing affordability in every 2026 decision▶ 1:18:59.

• Rep. Pettersen highlighted that PJM's fast-track interconnection process initially selected 51 projects (11.8GW) but a number dropped out months later due to transmission constraints▶ 2:39:09.

• Chairman Swett stated 42% of power keeping the grid reliable during Winter Storm Fern nationally came from natural gas, with over 75% from dispatchable sources combined (gas, coal, nuclear, petroleum)▶ 3:17:39▶ 3:18:04.

• Commissioner See said in New England, 40% of generation during Fern came from fuel oil or diesel due to insufficient gas pipeline infrastructure to the region▶ 2:33:22.

• Rep. Auchincloss and Commissioner See sparred over whether FERC should promote "legally durable signals" for offshore wind ("steel in the water") as much as for pipelines ("steel in the ground")▶ 3:21:23.

• Rep. Ocasio-Cortez pressed Chairman Swett on Con Edison's roughly 10% return on equity for transmission investment and whether FERC's rate-setting model is the most efficient for consumers, though Swett declined to confirm the specific 10% figure▶ 3:10:23.

• Commissioner Rosner and Commissioner See both acknowledged FERC cannot override a state's Clean Water Act Section 401 veto power over interstate pipelines like the Constitution Pipeline, calling it a matter only Congress could fix▶ 3:16:19▶ 3:58:25.

Metadata

CommitteeHouse Energy and Commerce Subcommittee on Energy
Chamber / CongressHouse · 119th Congress
DateFebruary 3, 2026
TypeHearing
Witnesses
The Honorable Lindsay See — Commissioner, Federal Energy Regulatory Commission
The Honorable Judy Chang — Commissioner, Federal Energy Regulatory Commission
The Honorable David Rosner — Commissioner, Federal Energy Regulatory Commission
The Honorable Laura Swett — Chairman, Federal Energy Regulatory Commission
The Honorable David LaCerte — Commissioner, Federal Energy Regulatory Commission
Videoyoutube
Transcript482 caption blocks · 35,388 words · 4:27:40 runtime
EventCongress.gov 118930