Modernization of the Organic Industrial Base

Defense Posture and Global ThreatsHouse Armed Services Subcommittee on Tactical Air and Land Forces · 2026-02-24 · 119th Congress
The House Armed Services Subcommittee on Tactical Air and Land Forces held a joint hearing with the Readiness Subcommittee to examine the Army's efforts to modernize its 23 government-owned arsenals, depots, and ammunition plants, many of which still rely on World War II-era infrastructure. Begins at 0:36:56
Transcript
Highlights

Title

Modernizing the Army's Munitions and Depot Industrial Base

Purpose

The House Armed Services Subcommittee on Tactical Air and Land Forces held a joint hearing with the Readiness Subcommittee to examine the Army's efforts to modernize its 23 government-owned arsenals, depots, and ammunition plants, many of which still rely on World War II-era infrastructure. Members and witnesses discussed the Army's $18 billion, 15-year organic industrial base modernization plan, the troubled Mesquite, Texas 155mm shell facility, novel energetics, declining ground vehicle mission-capable rates, and workforce and contracting concerns. Begins at0:36:56

Who spoke

Chairman Wittman0:36:56: Opened by describing the Army's goal of 100,000 155mm rounds per month and worry about boom-bust production cycles0:37:26; later pressed witnesses on the stalled Mesquite, Texas facility1:02:10 and on novel energetics like CL-201:09:41.

Rep. Norcross (D-NJ), Ranking Member0:40:24: Praised the joint hearing's focus on modernization and safety at depots, calling some facilities "a time machine"0:41:17; asked about the choke points in 155 production and whether Mesquite equipment would be repurposed1:13:291:17:18.

Rep. Bergman (R-MI), Readiness Subcommittee Chairman0:45:48: Noted Army mission-capable rates have declined since 2015 with maintenance costs up over 50%, tied partly to inadequate technical data rights0:46:170:46:59; criticized reliance on foreign munition manufacturers over idle domestic capacity0:47:54.

Rep. Garamendi (D-CA), Ranking Member0:49:03: Asked why readiness problems keep recurring despite the $18 billion plan0:52:11; later in a second round pressed for quarterly reporting on modernization metrics and raised concerns about defense contract quality favoring industry over taxpayers1:27:001:31:54.

The Honorable Brent Ingraham, Assistant Secretary of the Army0:53:09: Described the Pine Bluff enhanced use lease as a $1.3 billion industry investment in energetics0:56:52 and the Red River Army Depot advanced manufacturing effort0:55:52; later discussed technical data rights reform1:23:06 and mid-stream materials processing gaps for rare earths1:49:01.

Lt. Gen. Chris Mohan, Commanding General, Army Materiel Command0:58:06: Detailed a November 2025 OIB report and transformation implementation plan0:59:00; described the Operational Readiness Program that cut a unit's repair-parts consumption by $30 million and improved deployment readiness1:20:301:21:01; discussed digital twin and additive manufacturing efforts including Sky Foundry1:44:38.

Maj. Gen. John Reim, Joint PEO Armaments & Ammunition, Picatinny Arsenal1:03:29: Said the stop-work order at Mesquite remains in place amid negotiations with General Dynamics1:05:44; reported 155 production has risen from 14,000 to over 56,000 rounds per month1:04:45; said Radford's new nitrocellulose facility should be fully commissioned by April 20261:59:17; confirmed the U.S. was 100% dependent on China for antimony and pivoted to India while reopening a mine in Stibnite, Idaho1:47:471:48:09.

Rep. Sorensen (D-IL)1:40:56: Noted the anniversary of Russia's invasion of Ukraine1:40:56; asked about implementation of the Arsenal Workload Sustainment Act (Section 348)1:42:16 and progress on Sky Foundry's 3D-printed drone production goal of 10,000 per month1:44:14.

Rep. McGuire (R-VA)1:47:00: Questioned Reim on U.S. dependence on China and then India for antimony1:47:331:48:01; asked Ingraham about expanding solid rocket motor manufacturers1:48:33.

Rep. Mesmer1:52:34: Cited a new solid rocket motor site near Crane Army Ammunition Activity built by Prometheus Energetics1:52:34; asked about qualification timelines for additive-manufactured parts, told they range from 60 days to 14-15 months1:55:381:56:15.

Key moments

The Army initially planned 100,000 155mm rounds per month but current forecasts are lower; Ingraham said the Army does "not see us backing off from that number for a few years yet"1:13:531:14:21.

Reim confirmed the stop-work order at the Mesquite, Texas facility remains in place after more than two years without producing a single round, with negotiations ongoing with General Dynamics1:05:441:17:18.

155mm production has risen from about 14,000 rounds per month in 2022 to more than 56,000 today, with Scranton reaching 35,000 and a nearby commercial facility adding 21,0001:04:451:16:17.

Reim said Lake City's new artillery facility is the first new construction there since December 26, 1940, per Harry S. Truman's presidential library1:08:09.

The Army remains 100% dependent on foreign antimony sources — first China, now India — after China "weaponized the supply chain," while working to reopen a former WWII gold/tungsten/antimony mine in Stibnite, Idaho1:47:471:48:091:48:18.

Radford Army Ammunition Plant's new continuous-flow nitrocellulose facility is expected to be fully commissioned by April 2026, replacing an aging vat-based process Wittman described as requiring high humidity "so the place doesn't explode"1:58:061:59:25.

GAO found Army depot overhauls dropped from 1,278 in fiscal year 2015 to 12 in a more recent year, which Wittman cited as evidence of declining readiness1:36:07.

Mohan said industry partners currently owe the Army over $500 million in delinquent back-order repair parts1:22:11.

Reim said U.S. facilities are forced to import certain classes of nitrocellulose from the Czech Republic, France, and Korea and further process it in Canada because Radford cannot yet produce them domestically2:02:08.

Garamendi raised concerns that Defense Department contracts are often written to benefit the defense industrial base rather than protect Army and taxpayer goals, suggesting outside legal review of major contracts1:32:191:32:56.

Metadata

CommitteeHouse Armed Services Subcommittee on Tactical Air and Land Forces
Chamber / CongressHouse · 119th Congress
Date2026-02-24
TypeHearing
Witnesses
The Honorable Brent Ingraham — Assistant Secretary of the Army for Acquisition, Logistics, and Technology, Department of the Army
Lieutenant General Chris Mohan — Commanding Officer, Army Materiel Command
Major General John Reim — Joint Program Executive Office Armaments & Ammunition and the Commanding General, Picatinny Arsenal, Department of the Army
Videoyoutube
Transcript270 caption blocks · 15,542 words · 2:11:31 runtime
EventCongress.gov 118989