Budget Hearing – Architect of the Capitol

Legislative Branch Budget RequestsHouse Appropriations Subcommittee on Legislative Branch · 2026-03-18 · 119th Congress
The House Appropriations Subcommittee on Legislative Branch held this hearing to examine the Architect of the Capitol's (AOC) fiscal year 2027 budget request, a nearly $1.7 billion ask that represents a 105% increase over the FY26 enacted level [1:45:43], driven largely by deferred maintenance and a proposed multi-decade renovation of the Rayburn House Office Building. Begins at 1:44:54
Transcript
Highlights

Title

Fiscal year 2027 budget request for the Architect of the Capitol

Purpose

The House Appropriations Subcommittee on Legislative Branch held this hearing to examine the Architect of the Capitol's (AOC) fiscal year 2027 budget request, a nearly $1.7 billion ask that represents a 105% increase over the FY26 enacted level1:45:43, driven largely by deferred maintenance and a proposed multi-decade renovation of the Rayburn House Office Building. Architect Thomas Austin testified on the condition of Rayburn, swing-space and parking options, the Cannon renewal project's closeout, cybersecurity/life-safety needs, and lactation-room upgrades, while members pressed him on cost overruns, planning consensus, and project timelines. Begins at1:44:54

Who spoke

Chairman David Valadao (R-CA)1:44:54: Opened by citing the $1.7 billion request and 105% increase1:45:43; later questioned Austin on zero-based budgeting1:57:49 and on cost overruns in construction estimates1:59:39.

Ranking Member Adriano Espaillat (D-NY)1:46:09: Thanked Austin for installing the January 6 Capitol Police memorial plaque but criticized its late-night installation and inaccessible location1:46:40; asked whether AOC's organizational structure can manage the scale of the Rayburn project on time and budget2:04:27 and pressed on the 15–20 year Rayburn timeline2:06:12 and use of the O'Neill building for swing space2:07:13.

Ranking Member Rosa DeLauro (D-CT)1:48:06: Thanked AOC's HVAC team for warming the House floor1:48:34; said Rayburn's deterioration — corroded pipes, elevators, heating — poses a genuine safety risk requiring urgent resources1:51:041:51:54.

Thomas Austin, Architect of the Capitol1:52:45: Requested $1.6 billion total for FY27, citing deferred maintenance and the Rayburn master-plan initiative1:54:05; said Rayburn suffered two electrical fires, multiple mechanical failures, dozens of elevator/escalator outages, and 18 major leaks costing nearly $2 million in the past year1:55:12; estimated the full Rayburn renovation program at 15–20 years, running to roughly the mid-2040s2:06:12; said 84 of 85 campus elevators and 27 of 28 escalators were operational that morning2:13:38.

Rep. Dale Strong (R-AL)1:57:19: Asked about the Capitol Complex Master Plan's update cycle, last done in 20112:09:07; asked about contingency plans for major system failures before Rayburn renovation begins2:11:18 and the condition of the Longworth building2:11:47.

Rep. Chuck Fleischmann/"Laurel Lee" (R-FL)2:14:57: Asked what happens to the 184 member offices in Rayburn if the building becomes unusable, and about swing-space contingency plans2:14:58; asked about pedestrian screening investments on the south side of campus2:15:29.

Rep. Malloy (R)2:20:20: Asked when Cannon renewal interior work will be complete2:20:44; pressed on why minor-construction accounts are being tapped to cover cost overruns of up to 50%2:22:01 and whether AOC has workforce/project-management capacity for Rayburn2:24:17.

Rep. Steny Hoyer (D-MD)2:25:38: Asked which FY27 funding decisions affect the Rayburn schedule, eliciting that the $205 million parking garage request is the largest single item2:25:38; raised low water pressure in the Longworth building affecting fire suppression2:27:23.

Rep. Blake Moore (R-UT)2:28:18: Followed up on a prior request about lactation rooms, noting the AOC study found the campus is 16 stations short of need and that 25 of 61 existing lactation spaces don't meet quality standards2:29:03; asked about accommodations for families expected during America's 250th celebrations2:30:46.

Rep. Nick LaLota (R-NY)2:32:13: Expressed skepticism about the roughly $9 billion Rayburn swing-space proposal, questioning whether AOC had substantive consultations with the House Sergeant at Arms, CAO, and members themselves before presenting the options2:32:372:34:31; warned the project could balloon to $13–15 billion based on historical cost overruns2:36:17; asked when construction trailers will be removed from Lot One2:37:35.

Key moments

Austin said the FY27 request of $1.6 billion is driven mainly by compounding deferred maintenance and the Rayburn House Office Building renovation initiative1:54:051:54:26.

Austin detailed Rayburn's deteriorating condition: two electrical fires, multiple mechanical system failures, dozens of elevator/escalator outages, and 18 major leaks costing nearly $2 million in repairs over the past year1:55:12.

Austin estimated the total Rayburn renovation program at 15–20 years, running to roughly the mid-2040s, contingent on sustained annual funding2:06:122:06:42.

Austin said a one-year funding shortfall on critical-path "enabling projects" (parking garage, contractor space) would delay the entire multi-year Rayburn program by a year2:10:32.

The Library of Congress orientation gallery, meant to open for America's 250th celebrations, will now be delayed until at least July 2027 due to unforeseen floor delamination and a fire-rated ceiling redesign, causing over 200 days of delay2:02:422:03:56.

Rep. LaLota sharply challenged Austin over the roughly $9 billion Rayburn swing-space proposal, saying AOC lacked in-depth consultation with the Sergeant at Arms, CAO, and members, and predicted costs could grow to $13–15 billion based on past project overruns2:34:572:36:17.

Austin said the $205 million parking-garage request is the largest single FY27 Rayburn-related item, requested up front to shorten design/construction time2:25:382:26:07.

GAO-style cost-overrun concerns were echoed by Rep. Malloy, who noted some AOC construction projects have run up to 50% over estimate due to unforeseen historic-building conditions and bidding delays2:22:012:22:31.

Austin said the AOC study found the Capitol campus is 16 lactation stations short of need, with 25 of 61 existing spaces failing to meet quality standards; renovations of two Capitol Building suites are planned for summer2:29:032:29:58.

Austin acknowledged AOC does not have adequate swing space for a catastrophic system failure affecting more than about 12 offices, and would have to resort to ad hoc spaces like committee hearing rooms2:11:182:16:42.

Metadata

CommitteeHouse Appropriations Subcommittee on Legislative Branch
Chamber / CongressHouse · 119th Congress
Date2026-03-18
TypeHearing
Witnesses
Mr. Thomas Austin — Architect of the Capitol
Videoyoutube
Transcript294 caption blocks · 22,369 words · 2:39:43 runtime
EventCongress.gov 119058