Department of the Navy Fiscal Year 2027 Budget Request for Seapower and Projection Forces

Defense Posture and Global ThreatsHouse Armed Services Subcommittee on Seapower and Projection Forces · May 20, 2026 · 119th Congress
The House Armed Services Subcommittee on Seapower and Projection Forces held this hearing to examine the Department of the Navy's fiscal year 2027 budget request, focusing on shipbuilding rates, the new amphibious "Golden Fleet" and continuous ARG/MEU posture, the proposed nuclear-powered "battleship," submarine and reconstitution production, aviation and munitions programs, and unmanned systems. Begins at ▶ 0:08:09
Transcript
Highlights

Title

Navy and Marine Corps FY2027 shipbuilding, amphibious, and munitions budget

Purpose

The House Armed Services Subcommittee on Seapower and Projection Forces held this hearing to examine the Department of the Navy's fiscal year 2027 budget request, focusing on shipbuilding rates, the new amphibious "Golden Fleet" and continuous ARG/MEU posture, the proposed nuclear-powered "battleship," submarine and reconstitution production, aviation and munitions programs, and unmanned systems. Witnesses Jason Potter, Lieutenant Colonel Eric Austin, and Rear Admiral Mark Behning testified alongside members pressing on industrial-base capacity, reconciliation funding for shipbuilding, and design maturity for new platforms. Begins at▶ 0:08:09

Who spoke

• Chair Trent Kelly (R-MS)▶ 0:08:09: Opened by warning against divesting more hulls than are procured, called for sustaining two Virginia-class submarines a year and speeding amphib production▶ 0:08:49, and later questioned Potter on demand-signal stability and amphib maintenance turnaround▶ 0:27:40▶ 0:29:47.

• Ranking Member Joe Courtney (D-CT)▶ 0:10:25: Praised the $34 billion submarine request and wage-improvement funding that cut Southern New England shipyard attrition below 8%▶ 0:11:39, but criticized splitting the budget via reconciliation, noted $5.6 billion of shipbuilding funds (including six medium landing ships) sit behind reconciliation▶ 0:14:06, and called the battleship's $1 billion request — $610 million for long-lead items with no finished design and a projected $17.6 billion year-two ask — hard to justify▶ 0:14:57.

• Jason Potter, Performing Duties of ASN(RDA)▶ 0:16:48: Outlined a 34-ship request (18 battle force, 16 non-battle force) and 122 manned/63 unmanned vessels over five years reaching 450 ships by 2031▶ 0:18:12; later described the battleship's design reuse (Spy-6 radar, Aegis Baseline 10, Mark 41 VLS, A1B reactor)▶ 0:37:57 and said medium unmanned vessel solicitations drew "more than two dozen offers"▶ 1:00:41.

• Rear Admiral Mark Behning, Acting DCNO for Warfighting Requirements▶ 0:21:07: Described a high-low fleet mix teaming carriers, surface combatants, and submarines with unmanned platforms▶ 0:22:23; later detailed five lines of effort under the Amphibious Force Readiness Board to improve maintenance timelines and generate additional port engineers▶ 0:31:39▶ 0:32:30.

• Lieutenant Colonel Eric Austin, Deputy Commandant for Combat Development and Integration▶ 0:23:37: Said over 43,000 Marines are forward deployed and that current amphib readiness cannot sustain a continuous 3.0 ARG/MEU posture, with only three ARG/MEUs deployed now and gaps looming as one returns▶ 0:24:56▶ 0:30:39; discussed the medium landing ship program and metal-bending starting this fiscal year▶ 0:26:20.

• Rep. Rob Wittman (R-VA)▶ 0:38:47: Pressed on the shift of the battleship to nuclear power and the resulting demand on a single reactor supplier (BWXT) alongside Virginia, Columbia, and Ford-class needs▶ 0:39:14, and asked about interagency coordination with Commerce on industrial-base capacity▶ 0:43:23.

• Rep. Donald Norcross (D-NJ)▶ 0:43:50: Cited a March 4 GAO report on shipyard idle time and cascading readiness issues, and challenged how the Navy would raise shipbuilding tempo without adding shipyard capacity▶ 0:44:21; separately pressed Potter on whether the 30-year plan would offshore shipbuilding, drawing a "no" from Potter who compared any overseas orders to the Ice Pack icebreaker model▶ 0:47:34▶ 0:48:01.

• Rep. Scott DesJarlais (R-TN)▶ 0:49:20: Asked Behning about high-low mix tradeoffs in the Golden Fleet initiative▶ 0:49:20 and Potter about submarine tender delivery timelines, told they are expected online in the "early 2030s"▶ 0:51:48.

• Rep. Jack Bergman (R-MI)▶ 0:53:14: Highlighted Dahlgren's high-energy laser R&D▶ 0:53:43 and asked Austin how the Marine Corps is learning from Ukrainian drone and counter-drone operations, which Austin said is feeding a Drone Dominance Task Force and thousands of fielded attack drones▶ 0:54:27▶ 0:55:16.

• Rep. Ronny Jackson (R-TX)▶ 0:57:59: Raised subsea cable sabotage risks in the Baltic and Strait of Hormuz and asked Potter about domestic unmanned surface vessel production capacity▶ 0:59:16; Potter confirmed more than $2 billion in funding and over two dozen competitive USV offers▶ 1:00:10.

• Unnamed committee member (addressed by Potter as "Congresswoman")▶ 1:02:10: Invited Potter to visit a Baltimore-area shipyard site and pressed on how Congress can "trust but verify" that overseas shipbuilding jobs eventually return to the US▶ 1:03:14; also questioned Austin on why LSM funding sits in the mandatory/reconciliation portion of the budget▶ 1:05:32.

• Del. James Moylan (Guam, transcribed as "Molan")▶ 1:07:15: Asked about Marine Corps disaster relief after a typhoon hit Guam and the Northern Marianas▶ 1:07:40, Camp Blaz construction progress▶ 1:08:11, submarine tender maintenance capacity at Polaris Point▶ 1:08:41, and munitions resupply and ship-repair facility needs on Guam▶ 1:10:02▶ 1:11:17.

• Rep. Clay Higgins (R-LA)▶ 1:12:10: Challenged Potter on why smaller and regional shipyards with ready-to-build unmanned and autonomous vessel designs aren't being contracted while large shipyards struggle to keep up▶ 1:13:32; Potter acknowledged some Gulf Coast yards were overloaded with designs beyond their in-house naval-architecture capacity and proposed separating design from build contracts▶ 1:15:20.

Key moments

• Courtney said Virginia-class Block VI contract authorization from roughly 28 months ago faces new ambiguity from Section 8010 of the year-long continuing resolution; Potter said the Department is working with OMB and the committees to resolve it▶ 0:33:40▶ 0:34:03.

• Courtney called the battleship's budget trajectory "defies logic" given $1 billion requested this year (including $610 million for long-lead items) with no finished design, and $17.6 billion projected for year two▶ 0:14:57.

• Potter said the battleship will reuse proven systems — Spy-6 radar, Aegis Baseline 10, the Mark 41 vertical launcher, and the carrier's A1B reactor plant — while reserving space/weight/power for future lasers and railguns▶ 0:37:57▶ 0:38:17.

• Wittman warned that adding a nuclear-powered battleship to existing Virginia, Columbia, and Ford-class reactor demand creates a "confluence of demand" on a single reactor supplier, BWXT▶ 0:39:36▶ 0:42:11.

• Austin said current amphibious ship readiness cannot support a continuous "3.0" ARG/MEU posture; only three ARG/MEUs are deployed now, dropping to two soon and creating coverage gaps flagged by combatant commanders▶ 0:30:39▶ 0:31:08.

• Norcross asked "how the hell" the Navy plans to raise shipbuilding tempo roughly 40–75% without expanding shipyards; Potter cited wage increases, distributed shipbuilding, and Shipyard Infrastructure Optimization Plan master plans as the approach▶ 0:44:50▶ 0:45:46.

• Norcross challenged the 30-year plan's provision for overseas shipbuilding capacity; Potter said the answer is "no," current US shipyards are largely full with schedule delays, and any overseas orders would mirror the short-term Ice Pack icebreaker model paired with domestic investment▶ 0:48:01▶ 0:48:51.

• Potter said the medium unmanned surface vessel solicitation drew "more than two dozen offers," calling it "unheard of in Navy shipbuilding," with $2 billion in funding now available▶ 1:00:41▶ 1:00:10.

• Higgins said small and regional shipyards with tested, ready-to-contract unmanned vessel designs are being passed over while large shipyards struggle; Potter acknowledged Gulf Coast yards were overloaded with Navy-specified designs beyond their in-house capability and proposed separating design from build work▶ 1:14:29▶ 1:15:41.

• Courtney noted minimal funding this year for unmanned capabilities despite significant funding last year and last year's NDAA emphasis, urging a sustainable long-term strategy▶ 0:15:27▶ 0:15:56.

Metadata

CommitteeHouse Armed Services Subcommittee on Seapower and Projection Forces
Chamber / CongressHouse · 119th Congress
DateMay 20, 2026
TypeHearing
Witnesses
Mr. Jason Potter — Performing the Duties of Assistant Secretary of the Navy for Research, Development, and Acquisition, Department of the Navy
Lieutenant Colonel Eric Austin — Deputy Commandant of the Marine Corps for Combat Development and Integration, Department of the Navy
Rear Admiral Upper Half Mark Behning — Acting Deputy Chief of Naval Operations for Warfighting Requirements and Capabilities, United States Navy
Videoyoutube
Transcript164 caption blocks · 12,129 words · 1:17:35 runtime
EventCongress.gov 119324