Hearings to examine improving the Federal environmental review and permitting processes

Environmental Permitting and Water InfrastructureSenate Environment and Public Works · 2025-02-19 · 119th Congress
The Senate Environment and Public Works Committee held this hearing to examine how the federal environmental review and permitting process — governed by NEPA, the Clean Water Act, the Clean Air Act, and the Endangered Species Act — could be modernized to reduce delays and costs for energy, housing, and infrastructure projects. Begins at 0:17:01
Transcript
Highlights

Title

Reforming federal environmental review and permitting to speed projects

Purpose

The Senate Environment and Public Works Committee held this hearing to examine how the federal environmental review and permitting process — governed by NEPA, the Clean Water Act, the Clean Air Act, and the Endangered Species Act — could be modernized to reduce delays and costs for energy, housing, and infrastructure projects. Chair Capito and Ranking Member Whitehouse framed the session as the start of a bipartisan effort with the House and the Energy and Natural Resources Committee, while five witnesses representing energy, construction, homebuilding, labor, and clean-energy advocacy perspectives testified on specific reforms. Begins at0:17:01

Who spoke

Chair Shelley Moore Capito (R-WV)0:17:01: Opened by describing permitting delays in West Virginia projects, including a steel plant and the Mountain Valley Pipeline0:20:240:20:54, and laid out guiding principles for bipartisan reform0:21:51; later asked witnesses whether Congress must act together0:57:38 and questioned Booker on post-permit litigation1:00:28.

Sen. Sheldon Whitehouse (D-RI), Ranking Member0:23:39: Warned Democrats cannot support permitting reform unless the Trump administration ends what he called disregard for court orders0:24:26, defended offshore wind and clean energy investment0:25:510:26:44, and cited NERC's projected 18% winter peak demand growth and aging transmission0:27:13; later pressed witnesses on interagency process reform and early stakeholder engagement1:08:131:09:31.

Jeremy Harrell, CEO, ClearPath0:29:43: Said the U.S. needs to add roughly six energy projects a day (16,000 facilities by 2035) to meet demand0:30:34, proposed expanded categorical exclusions and judicial review reform0:31:280:33:39, and cited data that litigation delays projects an average of four years while agencies win 71% of challenges0:33:39; later estimated new transmission build-out versus grid-efficiency gains at roughly 75%/25%1:08:05 and cited Wyoming/North Dakota completing Class VI wells in under a year1:59:52.

Leah Pilconis, General Counsel, Associated General Contractors of America0:35:31: Recommended a uniform 150-day judicial review window for all critical infrastructure projects0:36:46, said current APA litigation exposure can run up to six years0:37:05, and said NEPA implementation should align with the Fiscal Responsibility Act0:37:34; later said Sackett-era Clean Water Act jurisdictional terms remain inconsistently applied across Army Corps districts1:13:09.

Carl Harris, Chairman, National Association of Home Builders0:40:59: Said 77% of buyers cannot afford a median-priced new home and every $1,000 added to a home's price locks out 106,000 households0:41:540:42:15; said jurisdictional determinations can take over a year and nationwide permits meant to take 60 days are taking nearly a year0:43:100:44:08; cited a $140,000 mitigation-credit cost on an Ohio project adding $10,000 per home0:45:08.

Brent Booker, General President, Laborers' International Union of North America (LIUNA)0:46:58: Said LIUNA represents over 500,000 workers0:46:58 and that offshore wind halts threaten thousands of union jobs, including a Martha's Vineyard-area project powering up to 600,000 homes0:50:19; argued litigation after permits are issued creates unpredictability that costs members paychecks1:01:10.

Nicole Pavia, Program Director, Clean Air Task Force0:52:38: Said about 2,600 gigawatts of mostly zero-emitting capacity sits stalled in interconnection queues0:54:03; said her organization's study found delays stem mainly from agency coordination gaps, insufficient staffing, and local/state misalignment rather than NEPA provisions themselves0:55:29; recommended consolidating national-interest transmission permitting under FERC0:56:49.

Sen. Kevin Cramer (R-ND)1:10:38: Praised the bipartisan tone with Whitehouse1:10:38 and pressed Pilconis and Harris on why Clean Water Act jurisdictional determinations remain necessary post-Sackett1:12:33, and on linear siting parity for transmission1:16:04.

Sen. Mark Kelly (D-AZ)1:16:36: Described Taiwanese businesses citing confusing multi-agency U.S. permitting as a deterrent to investment1:18:32, and asked how permitting delays affect clean-energy manufacturing in Arizona1:21:23.

Sen. John Curtis (R-UT)1:22:14: Asked how federal policy could support Utah's "Operation Gigawatt" geothermal and nuclear strategy1:23:16 and pressed on why transmission permitting reform stalls despite bipartisan interest1:25:15.

Sen. Alex Padilla (D-CA)1:28:05: Argued permitting delays are being worsened by DOGE-driven federal staffing cuts1:29:02 and asked about interregional transmission planning to reduce jurisdictional misalignment1:31:36.

Sen. Pete Ricketts (R-NE)1:33:12: Cited Nebraska's SIGMA program cutting a permitting process from 110 steps to 22 and from 180 days to 65 days1:36:12, and asked Pilconis about conflicting statutes like the Flood Control Act and Endangered Species Act1:34:15.

Sen. Adam Schiff (D-CA)1:40:33: Asked Harris how much of housing permitting delay is federal versus state/local1:40:33 and questioned Booker on the administration's offshore wind leasing suspension1:43:13, and asked Pavia why California's interconnection queue holds three times the capacity needed for state renewable goals1:45:05.

Sen. Jon Husted (R-OH)1:47:09: Described frustration with inconsistent federal regulators from his experience as Ohio lieutenant governor1:47:40 and asked all witnesses for concrete fixes to permitting delays affecting the CHIPS Act and power plant construction1:50:17.

Sen. Cynthia Lummis (R-WY)1:53:23: Asked about her "permit by rule" bill with Sen. Budd (the "Full Responsibility and Expedited Enforcement Act")1:53:54, and asked about Class VI carbon-well primacy delays, noting EPA has 151 pending applications with only four granted1:58:10.

Key moments

Harrell cited an analysis finding litigation delays fossil and clean energy projects by an average of four years even though agencies win 71% of challenges, and that 24% of transmission projects that finished environmental review still faced litigation, with agencies winning 88% of those0:33:390:34:03.

Harris said the average U.S. home price rose $90,000 over the last 2.5 years and that 24% of a new home's cost is tied to government regulation, split roughly evenly between federal and state/local1:00:161:41:03.

Whitehouse and Cramer's exchange showcased unusual bipartisan warmth, with Cramer joking he'd replay Whitehouse's remarks "to my Republican friends" to explain why he likes working with him1:10:38.

Pilconis said NEPA is the most litigated statute, with challenges taking up to 4.5 years to resolve at the appellate level, and recommended extending the existing 150-day statute of limitations (from MAP-21) to all critical infrastructure projects1:02:201:03:19.

Ricketts detailed Nebraska's permitting streamlining as governor, cutting a review process from 110 steps to 22 and permit issuance from 180 to 65 days1:36:12.

Schiff pressed Booker on the administration's offshore wind leasing suspension; Booker responded that "killing of wind jobs is killing of American jobs" and warned against government picking energy-sector winners and losers1:43:401:44:04.

Pavia said roughly 2,600 gigawatts of largely zero-emitting capacity sits stalled in interconnection queues, and described a "chicken and egg" problem where transmission isn't built without confirmed generation and vice versa0:54:031:46:00.

Lummis noted EPA has 151 pending Class VI carbon-well primacy applications but has granted only four, while Wyoming and North Dakota (which hold primacy) process wells in under a year1:58:101:59:52.

Booker proposed requiring agencies to make up-or-down permitting decisions with firm timelines and barring litigation from halting projects once permitted and under construction1:52:35.

Harris said homebuilders often avoid the lengthy approved jurisdictional determination (over a year) in favor of a faster but non-appealable preliminary determination that can still block use of the nationwide permit0:43:100:43:42.

Metadata

CommitteeSenate Environment and Public Works
Chamber / CongressSenate · 119th Congress
Date2025-02-19
TypeMeeting
Witnesses
(none listed in event metadata)
Videosenate-isvp
Transcript279 caption blocks · 14,442 words · 2:03:19 runtime
EventCongress.gov 336619