Hearings to examine Infrastructure Investment and Jobs Act implementation and case studies

Surface Transportation ReauthorizationSenate Environment and Public Works · February 26, 2025 · 119th Congress
The Senate Environment and Public Works Committee met to conduct oversight of the Infrastructure Investment and Jobs Act (IIJA) ahead of its September 2026 expiration, hearing from state, contractor, and city witnesses about which provisions are working and which need reform as the committee begins work on the next surface transportation reauthorization [0:17:30]. Begins at ▶ 0:16:51
Transcript
Highlights

Title

Senate EPW oversight of Infrastructure Law implementation and funding freezes

Purpose

The Senate Environment and Public Works Committee met to conduct oversight of the Infrastructure Investment and Jobs Act (IIJA) ahead of its September 2026 expiration, hearing from state, contractor, and city witnesses about which provisions are working and which need reform as the committee begins work on the next surface transportation reauthorization▶ 0:17:22. Democrats used the hearing to press witnesses on the Trump administration's freezing of previously awarded and appropriated grant funds, while Republicans focused on cost increases, permitting delays, and program flexibility. Begins at▶ 0:16:51

Who spoke

• Chair Shelley Moore Capito (R-WV)▶ 0:16:51: Opened by noting the IIJA's provisions expire at the end of 2026 and highlighted the $8.7 billion in unused obligation authority sent back to states via "August redistribution" in 2024▶ 0:20:29; criticized the prior administration's December 2021 policy memo and greenhouse gas performance rule as regulatory overreach struck down after litigation from 22 states▶ 0:20:57▶ 0:21:29; later questioned witnesses on EV charger construction pace and Buy America waivers▶ 1:45:35▶ 1:48:07.

• Sen. Sheldon Whitehouse (D-RI), Ranking Member▶ 0:22:13: Said roughly one-third of America's 620,000 bridges need repair, including nearly 42,000 structurally deficient▶ 0:22:47; detailed Rhode Island's Washington Bridge (19,000 vehicles/day, closed over a year) and the I-95 corridor's 15 bridges awaiting federal grant action▶ 0:24:28▶ 0:24:56; accused the administration of a "fog bank technique" of vague non-answers to stall court-ordered fund releases▶ 0:56:47; later tied EV-charger rollbacks and offshore wind opposition to fossil-fuel industry political contributions▶ 1:51:51▶ 1:52:14.

• Russell McMurry, Commissioner, Georgia DOT (testifying for AASHTO)▶ 0:29:03: Cited Georgia's 60% increase in bridge costs, 66% in resurfacing, and over 115% in widening projects▶ 0:32:40; said one grant took 31 months from notice to execution▶ 0:33:39; confirmed under Chair Capito's questioning that Georgia has five NEVI charging stations under contract but none built▶ 0:49:03▶ 0:49:06; described an office pooling federal resource agencies that cut permitting time up to 80% on some reviews▶ 0:59:48.

• Gary Johnson, VP, Granite Construction (testifying for Transportation Construction Coalition)▶ 0:34:47: Said states have committed $183 billion in IIJA highway/bridge formula funds across nearly every U.S. county, including 2,300 projects in West Virginia and almost 500 in Rhode Island▶ 0:35:14; urged Congress to preserve the Buy America aggregates exemption and cited a 14-month wait for one state's pump waiver versus much faster approvals elsewhere▶ 0:38:28▶ 0:38:56; noted 96,000 work-zone crashes and nearly 1,000 fatalities in 2022▶ 0:39:25; noted Texas cut its review process from 36 to 16 months under delegated federal authority▶ 1:01:24.

• Michael Carroll, Deputy Managing Director, Philadelphia Office of Transportation and Infrastructure▶ 0:40:47: Described the Connected Communities program reconnecting neighborhoods split by I-676 (Vine Street Expressway)▶ 0:41:11; cited the Belles Mills and Green Valley bridges serving over 13,000 vehicles/day awaiting repair▶ 0:44:16; confirmed to Sen. Kelly that halted disbursements disrupt contractor planning and statutory construction deadlines▶ 1:32:04; said the city has been awarded $20 million for EV charging infrastructure but has built none of a planned ~200▶ 1:22:12▶ 1:45:54.

• Sen. Jon Husted (R-OH)▶ 0:58:29: Asked witnesses how to shorten permitting review times, noting permitting sometimes takes longer than construction itself▶ 0:59:02; raised the idea of an "urgency waiver" for emergency projects, citing Philadelphia's I-95 bridge collapse fixed in 12 days▶ 1:02:42.

• Sen. Jeff Merkley (D-OR)▶ 1:04:00: Pressed Carroll on whether the funding freeze and EPA/DOT staff cuts will increase project costs and delays▶ 1:05:01▶ 1:06:34; said he could not find anyone in Oregon who thinks the freeze makes anything better▶ 1:07:07.

• Sen. Pete Ricketts (R-NE)▶ 1:09:33: Argued EV charging grants don't fit rural states like Nebraska, where cold weather causes ~40% charge loss and some towns are 45 minutes from a charger▶ 1:11:09; asked McMurray about funding flexibility across program "buckets" and August redistribution reform▶ 1:12:29.

• Sen. Alex Padilla (D-CA)▶ 1:17:07: Said the infrastructure law created 180,000 jobs in California▶ 1:17:07; described a Bay Area city whose DOT contact disappeared and grant agreement went unanswered▶ 1:18:04; noted the $1.8 billion Charging and Fueling Infrastructure program has been frozen despite statutory appropriation▶ 1:22:12.

• Sen. Lisa Blunt Rochester (D-DE)▶ 1:23:28: Referenced an 80-year-old bridge on a Delaware tour and asked McMurray about uncertainty's effects on project delivery▶ 1:25:14; asked Carroll about the Reconnecting Communities program and the Chinatown Stitch project▶ 1:27:56.

• Sen. Mark Kelly (D-AZ)▶ 1:29:01: Cited DOT's December announcement that over 11,400 bridges are being repaired under the Bridge Investment Program▶ 1:30:22; said an Arizona I-40 project repairing four 1963 bridges near the Navajo Nation capital has been halted 36 days by the funding freeze▶ 1:31:19.

• Sen. Ed Markey (D-MA)▶ 1:34:29: Highlighted Massachusetts's use of IIJA funds for Cape Cod bridges and passenger rail▶ 1:34:51; got Carroll to agree that bridge, transit-signaling, and pedestrian-safety projects can simultaneously provide equity and climate benefits▶ 1:37:23▶ 1:37:40▶ 1:37:49; promoted his All Aboard Act for passenger rail funding▶ 1:39:07.

• Sen. Angela Alsobrooks (D-MD)▶ 1:39:51: Said Maryland DOT has $330 million in already-awarded funding on hold▶ 1:40:47; got McMurray to confirm it is not normal for FHWA to halt a bridge project mid-construction due to an administration change▶ 1:43:52▶ 1:44:02.

Key moments

• McMurray confirmed under direct questioning from Chair Capito that Georgia has five NEVI-funded EV charging stations under contract but has not built any▶ 0:49:03▶ 0:49:06.

• Whitehouse said DOT's new grant terms would require a "high marriage rate and birth rate" for communities to qualify, and plans to unilaterally amend existing signed grant agreements to impose new conditions▶ 0:26:20▶ 0:26:46.

• Sen. Kelly said an Arizona I-40 bridge-repair project serving the Navajo Nation capital and West Coast port trade corridor has been halted for 36 days by the funding freeze▶ 1:31:19▶ 1:31:48.

• Sen. Alsobrooks said Maryland has $330 million in already-awarded IIJA funding on hold, and McMurray agreed it is not his experience for FHWA to abruptly halt bridge, resurfacing, or formula-funded projects mid-construction due to a change in administration▶ 1:40:47▶ 1:44:02▶ 1:44:07▶ 1:44:13.

• Sen. Padilla described a Bay Area city that lost its DOT contact overnight and has since received no response on a long-sought grant agreement▶ 1:18:04▶ 1:18:29.

• Johnson said one state DOT waited 14 months for a Buy America waiver for a submersible pump while two other states got the same product approved much faster▶ 0:38:56.

• Chair Capito and Sen. Whitehouse disagreed over EV charger construction pace: Capito blamed Biden-era compliance requirements for slowing deployment (71,000 public chargers exist nationally)▶ 1:54:36▶ 1:54:59, while Whitehouse argued the "chicken and egg" logic favors continued federal build-out and accused the administration of spending taxpayer money to rip out already-built chargers▶ 1:50:31▶ 1:51:23.

• McMurray said Georgia has seen 60% cost increases in bridge projects, 66% in resurfacing, and over 115% in widening projects since IIJA enactment▶ 0:32:40.

• Whitehouse linked fossil-fuel industry political contributions (at least $100 million to Trump's election, plus undisclosed dark money) to administration policies rolling back EV infrastructure and offshore wind▶ 1:52:14▶ 1:52:42.

• Sen. Kelly asked Carroll and McMurray, as a preliminary credibility check, whether Russia invaded Ukraine; both confirmed yes▶ 1:29:28▶ 1:29:29▶ 1:29:50.

Metadata

CommitteeSenate Environment and Public Works
Chamber / CongressSenate · 119th Congress
DateFebruary 26, 2025
TypeMeeting
Witnesses
(none listed in event metadata)
Videosenate-isvp
Transcript290 caption blocks · 12,752 words · 1:56:11 runtime
EventCongress.gov 336643