Hearings to examine Water Resources Development Act of 2026, focusing on U.S. Army Corps of Engineers projects, programs, and priorities

Appropriations Bill MarkupsSenate Environment and Public Works · 2026-02-25 · 119th Congress
The Senate Environment and Public Works Committee convened this hearing (February 25, 2026) to help develop the biennial Water Resources Development Act (WRDA) of 2026 and examine the Army Corps of Engineers' civil works projects, programs, and priorities. Begins at 0:15:39
Transcript
Highlights

Title

Water Resources Development Act of 2026 and Army Corps priorities

Purpose

The Senate Environment and Public Works Committee convened this hearing (February 25, 2026) to help develop the biennial Water Resources Development Act (WRDA) of 2026 and examine the Army Corps of Engineers' civil works projects, programs, and priorities. Witnesses Assistant Secretary of the Army for Civil Works Adam Telle and Lt. Gen. William H. Graham Jr., Chief of Engineers, testified on WRDA 2024 implementation, project delays, a new "Building Infrastructure Not Paperwork" reform plan, and disputes over funding freezes affecting Democratic-led states. Ranking Member Whitehouse participated remotely from Rhode Island, which was experiencing record snowfall. Begins at0:15:39

Who spoke

Chair Shelley Moore Capito (R-WV)0:15:39: Opened the hearing on developing WRDA 20260:16:12, cited West Virginia projects including the Bluefield Dam safety project protecting 150,000 people and $20 billion in infrastructure0:19:13, and pressed Telle on the status of the implementation plan required by Section 11020:34:49 and the $15 billion in unobligated, six-year-old funding0:38:42.

Sen. Sheldon Whitehouse (D-RI), Ranking Member0:20:54: Participating remotely due to record Rhode Island snowfall (37 inches)0:21:13, accused the Corps of politicized permitting favoring fossil-fuel donors and an "unprecedented" $11 billion funding pause affecting 12 Democratic states0:23:31; said inland flood funding has outpaced coastal funding 20-to-1 or 100-to-10:24:02 and warned against merging harbor and inland trust funds0:25:02.

Sec. Adam Telle, Assistant Secretary of the Army for Civil Works0:27:03: Said the Army has finalized implementation guidance for most WRDA provisions, with 19 of 552 provisions still needing guidance0:27:34; unveiled the "Building Infrastructure, Not Paperwork" plan of 27 initiatives, calling it the biggest transformation since 19860:29:49; later detailed $24 billion spent on flood risk mitigation since 2017, $9 billion of it coastal0:47:55.

Lt. Gen. William H. Graham Jr., Chief of Engineers0:32:25: Described the Corps' navigation, flood/coastal storm, and ecosystem missions, noting 746 dams and 14,000 miles of levees provide about $200 billion/year in avoided flood damages0:32:53, and an 86.2% on-schedule/on-budget delivery rate, up from 80% in September0:33:50.

Sen. Kevin Cramer (R-ND)0:48:33: Thanked Telle for work on a pipeline EIS0:49:24 and pressed on WOTUS jurisdictional determinations, urging clearer, technology-driven guidance for landowners0:51:59.

Sen. Jeff Merkley (D-OR)0:55:57: Criticized unanswered questions for the record from the September hearing0:56:19; pressed on Columbia River salmon hatchery funding, citing a $160 million recapitalization backlog0:58:13, and on a stalled dredging study and hydropower deauthorization report stuck at OMB1:02:05.

Sen. Pete Ricketts (R-NE)1:04:01: Cited the 2019 Nebraska floods that killed four people and cost $3 billion1:04:31, questioned whether flood-control and endangered-species priorities are properly ranked in the Missouri River Master Manual1:05:46, and raised pallid sturgeon recovery metrics transparency1:08:47.

Sen. Alex Padilla (D-CA)1:11:11: Said California's project process is "fundamentally broken," citing $126 million stripped from Sacramento's FY2025 work plan and $11 billion in paused blue-state funding announced by OMB on October 171:12:23; pressed Graham on the San Francisco waterfront coastal flood study, told its cost estimate is $17–32 billion against a $2–3 billion annual construction budget1:16:05.

Sen. John Boozman (R-AR)1:19:41: Thanked Telle for Corps response to the Darnell spillway failure1:19:41; asked about inconsistent district-to-district decisions1:20:51 and Section 214 funding agreements1:22:33; described a stuck dam gate in Arkansas as a cybersecurity vulnerability lesson1:24:44.

Sen. Angela Alsobrooks (D-MD)1:26:06: Raised Maryland priorities including Mid-Chesapeake Bay ecosystem restoration and Poplar Island dredge-material capacity1:26:26, and said an October 30 letter to Telle protesting the funding freeze remains unanswered1:31:18.

Sen. Lisa Blunt Rochester (D-DE)1:32:58: Asked about implementing environmental infrastructure authorities for Delaware counties1:34:23, challenging Telle's NASA/"science fair" analogy1:36:23; asked whether paused projects were exclusively in Democratic states1:38:26.

Sen. Mark Kelly (D-AZ)1:40:15: Pressed on the Flagstaff flood project's 902 cost-validation limit, securing a commitment the study will be done by May 2026 in time for WRDA1:41:31; got Graham to admit the Winslow Levee project will miss WRDA 2026 and target 2028 instead1:44:00, and that 29 projects nationwide are under 902 review1:45:02.

Chair Cynthia Lummis (R-WY), acting chair1:46:16: Asked about harmful algae blooms in Western reservoirs1:46:40 and snowpack/soil moisture monitoring amid historically low Colorado River Basin flows1:49:02.

Sen. Adam Schiff (D-CA)1:51:47: Questioned why four canceled Sacramento River flood projects were in California and Washington, both Democratic states1:52:18, obtained Graham's commitment those four projects will proceed this year1:54:12; challenged Graham on the L.A. River ecosystem restoration report missing its promised WRDA 2026 deadline1:54:52, asking directly whether the delay was political1:57:00.

Sen. Dan Sullivan (R-AK)1:57:50: Pressed on the Juneau/Mendenhall Valley glacial flood crisis affecting thousands of homes1:59:15, submitted a news article on the Corps' reported pivot away from a levee-cap solution2:01:03, and pushed for a clear commitment to short-, medium-, and long-term solutions2:02:36.

Key moments

Whitehouse said the Corps issued implementation guidance for only 3 of over 180 WRDA 2024 provisions and accused the administration of pausing $11 billion in funding for 12 Democratic-represented states, citing OMB Director Russell Vought's stated rationale0:22:320:23:31.

Telle countered that of 552 total provisions across the last three WRDAs, only 21 required implementation guidance, with two signed Monday and five more coming in weeks0:35:480:36:16.

Telle disclosed $45 billion in appropriated but unexecuted Corps funding, including $15 billion more than six years old, calling it "a shame"0:29:210:39:35.

Padilla detailed specific frozen/stalled California projects: $126 million cut from Sacramento's work plan, a halted San Francisco waterfront report, stopped work on the L.A. River ecosystem project, and a three-month-stalled recycled water pipeline1:11:591:13:161:13:41.

Graham revealed the San Francisco waterfront coastal flood project's cost estimate has ballooned to $17–32 billion against the Corps' $2–3 billion annual national construction budget, with engineering only about 10% mature1:16:051:17:03.

Schiff pressed Graham on whether the L.A. River report delay was a "political decision," and Graham denied political direction while acknowledging the Corps could not deliver on its September commitment1:57:001:57:25.

Kelly got Graham to admit the Winslow Levee project—fully locally funded since 2024—will miss WRDA 2026 due to a 902 cost-validation limit triggered by immature (5%) engineering at authorization, targeting WRDA 2028 instead, and Graham called this cycle the "spiral of doom"1:43:071:44:001:46:07.

Sullivan revealed the Corps' rough estimate for a Juneau glacial-flood tunnel solution is six to ten years, while 2,855 homes in the Mendenhall Valley remain at risk of flooding again this summer2:10:172:11:10.

Whitehouse noted inland flood project funding has historically outpaced coastal funding by 20-to-1 to 100-to-1; Telle responded that of $24 billion spent on flood mitigation since 2017, $9 billion went to coastal storm risk0:24:020:48:28.

Ricketts and Graham sparred over whether flood control is formally ranked above endangered species protections in the Missouri River Master Manual; Graham said "life, health and safety" is always the top priority despite the manual not ranking purposes1:06:301:06:49.

Metadata

CommitteeSenate Environment and Public Works
Chamber / CongressSenate · 119th Congress
Date2026-02-25
TypeMeeting
Witnesses
(none listed in event metadata)
Videosenate-isvp
Transcript352 caption blocks · 17,560 words · 2:16:15 runtime