Hearings to examine Department of Energy's implementation of President Trump's May 2025 nuclear energy executive orders

Nuclear Regulation and EPA NominationsSenate Energy and Natural Resources · March 19, 2026 · 119th Congress
The Senate Energy and Natural Resources Committee held this hearing to examine the Department of Energy's implementation of four executive orders on nuclear energy signed by President Trump in May 2025, which directed advanced reactor deployment, NRC reform, accelerated reactor testing, and rebuilding the domestic nuclear industrial base. Begins at ▶ 0:17:09
Transcript
Highlights

Title

DOE implementation of Trump's nuclear energy executive orders

Purpose

The Senate Energy and Natural Resources Committee held this hearing to examine the Department of Energy's implementation of four executive orders on nuclear energy signed by President Trump in May 2025, which directed advanced reactor deployment, NRC reform, accelerated reactor testing, and rebuilding the domestic nuclear industrial base. Chair Lee and Ranking Member Heinrich led the panel in questioning DOE Assistant Secretary for Nuclear Energy Theodore Garrish, Idaho National Laboratory Director John Wagner, and Kairos Power CEO Dr. Mike Laufer on reactor pilot programs, fuel supply, cost overruns, and international competition. Begins at▶ 0:17:09

Who spoke

• Chair Mike Lee (R-UT)▶ 0:17:09: Opened by summarizing the four executive orders and their goals — deploying advanced reactor tech, NRC reform, and rebuilding the industrial base▶ 0:17:39; later touted the ARC Act addressing cost-overrun risk▶ 1:40:02 and predicted major near-term milestones from SMRs and micro reactors▶ 1:35:27.

• Sen. Martin Heinrich (D-NM), Ranking Member▶ 0:23:17: Warned the U.S. nuclear industry needs greater policy confidence, noting a proposed budget would have cut Office of Nuclear Energy funding by over $400 million▶ 0:26:10; touted his Advancing Research and Nuclear Fuel Recycling Act to address used fuel at 121 U.S. sites▶ 0:27:04.

• Theodore Garrish, Assistant Secretary of Energy for Nuclear Energy▶ 0:29:27: Outlined four priorities — domestic uranium enrichment, new reactor starts, international exports, and completing the fuel cycle▶ 0:30:14; said the U.S. lost most of its 20% share of the domestic enrichment market after Russian import cutoffs eliminated 3.5 million separative work units▶ 0:30:33; reported 24 states expressed interest in hosting nuclear "industrialization" campuses, with 4-5 serious proposals due April 1▶ 0:39:01.

• Dr. John Wagner, Director, Idaho National Laboratory▶ 0:40:41: Said INL's DOME facility will be ready for its first demonstration reactor by month's end and the Kairos reactor installs next month▶ 0:42:05; flagged a statutory gap in Section 202 that could subject private-company reactors on lab sites to unintended NRC jurisdiction▶ 0:57:01; said no commercial-scale HALEU production exists outside Russia and China▶ 0:45:52.

• Dr. Mike Laufer, CEO and Cofounder, Kairos Power▶ 0:46:37: Described Kairos's milestone-based DOE agreement worth $125 million, modeled on NASA's Commercial Orbital Transportation Services program▶ 0:49:53; said the company's first customers are Google and TVA, with Hermes 2 as the first reactor under the industry's first-ever nuclear power purchase agreement▶ 0:49:26.

• Sen. Catherine Cortez Masto (D-NV)▶ 0:24:21: Pressed on spent-fuel management recommendations sent to the White House, confirming the administration's continued opposition to Yucca Mountain funding▶ 1:06:51; stressed nuclear waste policy needs updating before further reactor deployment▶ 1:10:06.

• Sen. Cindy Hyde-Smith (R-MS)▶ 1:11:02: Cited Mississippi's Grand Gulf Nuclear Station and asked how to reassure the nuclear supply chain to cut cost overruns and construction disruptions▶ 1:12:15.

• Sen. Ruben Gallego (D-AZ) [0:17:47 caption garbled as "Supsen. Gallego" — 1:17:47]: Asked about outreach to communities near military bases for microreactor siting under the national-security executive order▶ 1:18:56 and how the ARC Act could speed deployment▶ 1:20:49.

• Sen. John Barrasso (R-WY) [0:22:55 — actual 1:22:55]: Highlighted the NRC's first-ever construction permit for a commercial non-light-water reactor, in Wyoming▶ 1:23:53; noted Russia and China account for about 95% of nuclear reactors under construction globally▶ 1:25:29; asked about the Energy Dominance Financing Program's milestones▶ 1:26:02.

• Sen. Lisa Murkowski (R-AK)▶ 1:29:30: Asked how to prevent fuel supply from becoming a pacing constraint for deployment▶ 1:30:30; pressed for micro-reactor demonstration opportunities in remote Alaska communities reliant on costly diesel power▶ 1:32:19.

• Sen. Jim Risch (R-ID) [1:41:11 — labeled Chair Lee in transcript, corrected via context]: Discussed the ARC Act's aim to address cost-overrun risk, citing Vogtle's cost escalation from an estimated $14 billion to over $30 billion▶ 1:41:31; noted a "constant stream" of new private investors entering the nuclear industry▶ 1:43:52.

• Sen. Steve Daines (R-MT)▶ 1:46:57: Discussed micro reactors for remote/distributed power and Starlink Mini pairing▶ 1:47:25; presented a study finding advanced nuclear could be sited at Montana's Coal Strip plant, adding an estimated 680 jobs▶ 1:54:07; asked about expanding enrichment partnerships with countries like Kazakhstan▶ 1:56:33.

Key moments

• Garrish said the U.S. lost most of its 20% share of global enrichment capacity after Russian import cutoffs eliminated 3.5 million separative work units, and DOE has made $2.7 billion in awards to rebuild domestic enrichment▶ 0:30:33▶ 1:26:09.

• Garrish said DOE received 11 applications for the pilot reactor program and expects three or four to achieve criticality by the July 4 target date▶ 0:34:04▶ 0:34:24; Wagner said he was initially skeptical but is "no longer skeptical" that three reactors will reach criticality by July 4▶ 0:43:28.

• Wagner asked Congress to clarify a statutory ambiguity in Section 202 that could improperly subject privately funded reactors demonstrated at national labs to NRC commercial licensing requirements▶ 0:57:01▶ 0:58:03.

• Heinrich noted a proposed budget in the same year as the executive orders would have cut Office of Nuclear Energy funding by over $400 million, and questioned whether administration support extends beyond firms close to the White House▶ 0:26:10▶ 0:26:37.

• Cortez Masto confirmed with Garrish that the administration's opposition to Yucca Mountain, and its funding, remains unchanged▶ 1:06:51▶ 1:07:03.

• Wagner cited the Vogtle nuclear project's cost escalation from an estimated $14 billion to over $30 billion as the central deterrent to utility investment in new large reactors▶ 1:41:31.

• Barrasso noted Russia and China account for about 95% of nuclear reactors currently under construction worldwide, framing U.S. export policy as a competitiveness issue▶ 1:25:29.

• Laufer said Kairos received $125 million from DOE under a milestone-based technology investment agreement modeled on NASA's Commercial Orbital Transportation Services program, and is "only paid when we deliver results that matter"▶ 0:49:53▶ 0:50:21.

• Daines cited a 2025 study finding advanced nuclear at Montana's Coal Strip site could retain 60-74% of current plant workers and add roughly 680 jobs, leveraging existing transmission including the North Plains Connector▶ 1:54:07▶ 1:55:31.

• Wagner said no commercial-scale HALEU production currently exists outside Russia and China, calling the fuel cycle "our most critical vulnerability"▶ 0:45:52▶ 1:28:09.

Metadata

CommitteeSenate Energy and Natural Resources
Chamber / CongressSenate · 119th Congress
DateMarch 19, 2026
TypeMeeting
Witnesses
(none listed in event metadata)
Videosenate-isvp
Transcript267 caption blocks · 13,700 words · 2:00:12 runtime
EventCongress.gov 338065